Transformer transport, installation & energization
Installation of transmission transformers up to 220kV under a rigorous technical procedure: safe, accurate and efficient.
Services
Turnkey, from factory to substation
With experienced engineers and specialised equipment, MEEPOWER covers every stage: transport, positioning, installation, connection, testing and adjustment, through to acceptance and commissioning.
All work complies with power-industry standards and EVN regulations, delivering 220kV transmission systems that run stably, reliably and sustainably.

Our process
- 01
Transport
Heavy-haul transport planning, route survey, reinforcement and supervision throughout the journey.
- 02
Positioning
Unloading, jacking and precise positioning on the foundation according to the substation design.
- 03
Installation
Mounting bushings, radiators, conservator, tap changer and accessories; vacuum treatment and oil filling.
- 04
Connection
Primary and secondary connections, control and protection circuits, and the cooling system.
- 05
Testing & adjustment
Site tests, oil analysis and adjustment of equipment to standard.
- 06
Acceptance & energization
Acceptance with the operator, energization and post-energization monitoring.
Featured project
220kV-250MVA transformer – Binh Tan 220kV substation
Two 220kV-250MVA transformers designed and manufactured by MEEPOWER were transported from the factory, installed and successfully energized at Binh Tan 220kV substation in 2025, and accepted by Ho Chi Minh City Power Corporation in October and November 2025.

Leaving the factory gate 
Arriving at Binh Tan substation 
Final assembly 
MEEPOWER leadership at energization
Need a transport & installation plan for your project?
Send us the substation, rating and schedule – a MEEPOWER engineer will get back to you.