On 24 October 2021 at Thanh Nghi 110kV substation, Ha Nam province, Dong Anh Manufacturing Electrical Equipment JSC (DONGANHMEE) worked with the Grid Project Management Board, Ha Nam Power Company and other parties to energize and commission transformer T1 110kV-40MVA, completing the 110kV transformer supply package of the project to upgrade transformer T1 at Thanh Nghi 110kV substation, Ha Nam province.


40MVA-110kV transformer at Thanh Nghi 110kV substation, Ha Nam province
DONGANHMEE is proud that handing over the transformer at Thanh Nghi 110kV substation contributes practical benefits to the region’s socio-economic development: strengthening the regional power system, securing a stable supply and supporting the development of Vietnam’s transmission grid.